Gwanara road project: Kwara govt admits contracts inflation eight months after TheICIR report

Date: 2022-06-29

Kwara state government (KWSG) has admitted that the contract sum for the Ilesha Baruba – Gwanara road project was inflated by ?751,551,647.22, this is coming eight months after the ICIR-funded report.

The government also set September as the new date for the project completion

In 2020, a Kwara-based civil society organisation Elite Network for Sustainable Development, ENetSuD, made contracts inflation allegation against the government through a memo sent to the governor, AbdulRahman AbdulRazaq.

However, the Ministry of works denied allegations through an official press release by the Commissioner, Rotimi Iliasu, which was also followed by denials on various radio stations.

Eight months after the investigations which found out that eight years after, controversy and inflation has slowed down Ilesha-Baruba – Gwanara road project, the government wrote to ENetSuD highlighting the various administrative steps taken to address the allegations, while noting that the Bill of Engineering Measurement and Evaluation (BEME) has been re-calculated.

The letter reads in part: “As an administration committed to deepening transparency and accountability, the Governor immediately ordered discreet investigations into the matter with a view of unraveling the truth in the interest of the public.

“These investigations involved two different panels: an intra-ministerial panel in line with the civil service rules and another one chaired by His Excellency, the Deputy Governor Mr. Kayode Alabi.

“The investigations involved an invitation to Sanisi Partnership Ltd, the consulting firm for the Ilesha Baruba – Gwanara road project since 2013, who was asked to give accounts of the contract to determine the veracity of the issues raised by your organization [ENetSuD].

“Guided by the May 26, 2021 expert opinion of the consultant who provided the updated BEME with which they are executing the contract, the two panels have established that the 'Harmonized BEME' given to you [ENetSuD] was indeed incorrect and full of errors.

“We concede that the misconception in the public about this issue was clearly borne out of costly errors and lack of due diligence by some officials of the Ministry of Works and Transport.

“It is important to inform you (EnetSuD) that a final memo on the issue dated April 12, 2022 has recommended appropriate measures to be taken concerning the civil engineering staffers involved in the preparation of the faulty BEME.

“Among others, the costly development, as you (EnetSuD) may be aware, has also since led to immediate retooling of the due diligence mechanisms of not just the Ministry of Works and Transport but other Ministries, Departments, and Agencies of Kwara State Government to prevent such flops in the future”, the government explained.

While reacting to the latest development, the ENetSuD Coordinator Alagbonsi Abdullateef said the government response came late after 18 months of the initial allegation which prompted ICIR report.

He however said they are satisfied with the steps the government has taken.

He added that a lack of timely communication from the government to its partner in the social audit of projects will not help the government in its anti-corruption fight, as corruption can't be fought in silence.

He said confidence-building is key to the success of any partnership in the public interest.

He added that the new BEME provided by the KWSG (which supersedes the faulty one earlier provided in error) will be used to do a technical evaluation of the project when it is completed, as the government reported the current status of the project as 71 percent.

“Similarly, as a show of good faith that this organisation has nothing against the government, ENetSuD would like to inform the public that the new BEME lays to rest any previous allegations of contract inflation in the BEME for Ilesha Baruba – Gwanara Road in Baruten Local Government Area of Kwara State,” Alagbonsi said.

Road will be completed in September – Works Commissioner

When the ICIR visited the site this June work has resumed different from the stage at the last visit.

The commissioner for works and transport Rotimi Ilyasu who spoke with our reporter during an inspection of the site said the current total of work done on the road is presently at 72 per cent.

He added that a total of 23 kilometers out of the 33 has been asphalted and efforts are ongoing to ensure that the job is completed in September.

According to him “we are looking at September 2022 at completing this road, hopefully the rains will allow for speedy work,” he said.

When asked about the challenges encountered, he says “no challenges whatsoever, except the price of materials that has skyrocketed. A tonne of asphalt when we started last year was 27, 000 naira but the same tonne is 60,000 naira, but we are looking at what we can do,” he said.

The Speaker of the State House of Assembly, Yakubu Danladi-Salihu, who is an indigene of Gwanara assured that the government is committed to completing the road as promised.

He said “What we met on the ground and where we are today is a great difference. This government is committed to deliver this road, it a promise to our people and the government is working to ensure the promise is fulfilled.”

“The government has just released another tranche of money to ensure the work gets done,” he said.

The Chairman of the Transition Implementation Committee of Baruten local government AbdulRasheed Ibrahim-Lafia said “We are very grateful that work is ongoing on the road and we believe it will be completed very soon.

“The major occupation of our people is farming and these farm produce needs to get to the market to boost the economic of activities of this area but the bad road has been major hindrance.

“I believe when this road is completed the economic activities of this area will be greatly improved which will in turn boost the economy of the state as whole, “he said.

A resident of Gwanara Ibrahim Mohammed who expressed happiness at the rate of work done, said when completed the road will improve the economy of the area.

He however appealed to the state government to expedite action on the construction.

“We are appealing to the state government to ensure the road is completed and we pray for Almighty Allah to continue to give them wisdom to continue to pilot the affairs of the state,” he added.

However, another resident of the area Musa Idris Buko, condemned the pace of work on the project, “The pace of work on the road is unimpressive. It seems very slow and not genuinely being executed to ameliorate the sufferings of the people, but to score political points. The non-completion of that road by Gov. AbdulFattah Ahmed's administration earned the last administration the wrath of the people.

Source

 

Cloud Tag: What's trending

Click on a word/phrase to read more about it.

Quranic Recitation Competition     Tanke     Ayo Adeyemi     IFK     Bayer Nigeria Limited     Musa Aibinu     Rachael Obisesan     Kaosarah Adeyi     Olokoba Sulyman     Pilgrims Board     Radio Kwara     Turaki Of Ilorin     Abdul-Rahoof Bello     IsDB     Yekini Adio     Kwara State Health Insurance Agency     Hijab     Islamic Development Bank     Tanke Road     Ashiru     Pakata Development Association     Bibire Ajape     Sidikat Alaya     Oko     Okedare     Abatemi Usman     Tunde Oyawoye     Gafaru Olayiwola Olorisade     ITP     Lawal Jimoh     Yusuf Lanre Badmas     Abdulrahman Abdulrasak     Clement Yomi Adeboye     Ejidongari     UTME     Maimunat Oloriegbe     Bisi Oyeleke     Frootify     Joseph Alex Offorjama     Abdulraheem Olesin     Owo Arugbo     Habeeb Abdullahi Al-Ilory     Bilikisu Oniyangi     Shettima Of Ilorin     Azeez Bello     Photo News     Alikinla     International Vocational Centre     Jaiz Bank     Asa LGEA School     John Olobayo     Kawu Baraje     PharmAccess Foundation     Abdulrasheed Na\'Allah     COVID     Offa Grammer School     Balogun Ajikobi     Kola Shittu     Opolo Global Innovation Limited     Abdulganiyu Oladosu     Akorede     Lafiagi     Rex Olawoye     Hauwa Nuru     Adisa Logun     Saeedat Aliyu     Local Government Pension Board     Fatimah Abdulkadir     Undergraduate Bursary     Tafida     New Naira Notes     AGF Abdulrazaq     Kwara South     KWASEIC     Ilesha-Baruba     NULGE     Pacify Labs    

Cloud Tag: What's trending

Click on a word/phrase to read more about it.

Oloyede     Communication Network Support Services     Kwara Pdp     Abubakar Ndakene     George Innih     Okin High School     Mope Dasuki Belgore     Siraj Oyewale     Emmanuel Olatunji Adesoye     Akom Construction And Engineering Synergy Ltd     Yeketi     Olubukola Kifayat Adedeji     Kisira     Maryam A. Garuba     Ahman Patigi     Pakata Development Association     Olomu     Ilorin East     Coronavirus     QuickWin     Aishat Sulu-Gambari     Neuropsychiatric Hospital     Ayo Opadokun     Taofik Abiodun Ahmed     Olufolake Abdulrazaq     Isaac Aderemi Kolawole     Michael Nzwekwe     Ahmed Idris Mohammed     T And K FOODS     April 11     Otoge     Lafiagi     Rice Farmers Association Of Nigeria     Sola Saraki University     Hassan Abdulazeez Elewu     Olaiya Zuberu     Suleiman Mora Omar     Ademola Kiyesola     Saka Adeyemo     Kayode Zubair     Ahmed Alhasssan     Imodoye Writer’s Enclave     Niyi Ogundiran     Saudat Abdulbaqi     Yomi Ogunsola     Makama Of Ilorin     Mustapha Olanipekun     Adam Abdullahi Al-Ilory     John Olobayo     Sardauna Of Ilorin     Is\'haq Modibbo Kawu     Bank Of Industry     Sulyman Atolagbe Alege     Sabi     Imam Gambari     Kwara State Council Of Chiefs     Otuka     Bisi Kristien     Garba Ayodele Wahab     Minister     Kaiama     Galland Marcias     Ayodele Kuburat Olaosebikan     Okoolowo     Basic Education Certificate Examination     Academic Staff Union Of Universities     KWATMA     Adesina Simon Sodiya     Emir Of Lafiagi     Adisa Logun     Ojo Fadumila     Muslimah Entrepreneurship Forum     Abdulrazaq Aiyelabegan     Salihu S. Yaru     Kudirat Arinola Lawal     Owu Fall     Olusola Saraki