Why Tunde Idiagbon Flyover Project Is Delayed – Kwara Govt
Kwara State government has attributed the delay in the completion of Tunde Idiagbon Flyover project on University of Ilorin (UNILORIN) Road, Tanke, Ilorin, the state capital to market forces and climatic challenges.
The commissioner for works, Engr Rotimi Ilyasu, who spoke on the project, said the delay in the project completion, which was started over a year ago, was due to weather challenges and market forces.
He said that work on the flyover project has reached between 85 and 90 percent completion.
He, however, said that weather conditions had slowed down the rate of work, explaining that recent rainfalls had washed away earth work on surfaces of the road.
“In a couple of weeks, hopefully before May 29, it will be ready for use. Actually, both sides of the flyover are partially open for motorists now, especially in the evening when work is not done. All hands are on deck to deliver a quality job. This is a project we can't take chances on. And so far, it's been very good,” he added.
He identified weather challenges and undulating market prices as some of the factors responsible for the delay in delivering the project to the public.
But, the residents of the area have lamented the inconvenience the delay of the project has caused them.
Those who spoke with LEADERSHIP Friday included commuters and shop owners on the project route.
Two residents, Mr John Abidemi and Olagoke Kolade, however, expressed appreciation to the state government for embarking on the project aimed at easing traffic gridlock on the ever-busy Tanke Road.
They said, “This area used to witness heavy traffic jams. With this, we can see that achievements are speaking for the governor among his peers in the All Progressives Congress (APC).
“However, we residents of the Tanke area feel that the project should have been completed by now knowing that this project has a deadline. This is the rainy season and we're yet to get the project completed. We only hope that the project will be delivered for the use of the general public.”
They called on the government to complete the project on time to ease the inconveniences being experienced.
Mrs Opemipo Shade, who said that development does not come to any society without some level of suffering or hardship, however, said that some people were being deprived of their socio-economic livelihood along the route.
“So, we call on the state to expedite action on the project and commission it for the use of the people, especially the students, and motoring public,” she stated.
Cloud Tag: What's trending
Click on a word/phrase to read more about it.
Musa Alhassan Buge National Association Of Nigerian Students Modibbo Kawu Joseph Yemi Ajayi Wahab Abayawo Senate President Mumeen Lah Aliyu Kora-Sabi Saliu Ajibola Ajia The Herald Mansur Alfanla Bayo Lawal Adijat Adebiyi Ridwan Agboola Abdulhakeem Adelaja Amao Ibrahim Orire Abdulmumini AbdulRazaq Kwara United FERMA Abdullahi Samari Kwara University Of Education Jamiu Oyawoye Ekiti Turaki Of Ilorin Assayomo Moji Makanjuola Kisira Yusuf AbdulRasheed Rabiu Kwankwaso Mohammed Kamaludeen Kubra Kazum Umar Danladi Shero Bolakale Ayo SSA Youth Engagement Kwara Muslim Pilgrims Welfare Board Igbomina Kale Bayero Goodluck Jonathan Alliance For Democracy Kale Kawu Abdulganiyu AbdulAzeez Saheed Popoola Tosin Saraki KWTV Gamji Members Association Garba Idris Ajia Ajibola Saliu Ajia Aminat Omodara Busari Toyin Isiaka Iyabo Adewuyi Taofeek Ibraheem Ghali Alaaya Agboola Babatunde Zulu Gambari Sam Onile Arik Temi Kolawole Ganmo Power Sub-Station Isiaq Khadeejah Katibi Ibraheem Adeola Christopher Odetunde Ayodele Shittu Olatunde Olukoya Olatunji Bamgbola Shehu Salau Oke-opin KFA Idiagbon Yemi Sanni Amoyo New Naira Notes Mary Arinde Ayobola Ipinlaiye Baba Isale Ahmad Uthman Rueben Parejo Laboratory-to-Product